Title: An important departure from traditional project management is that critical chain project management ... Post by: thegingercoffee on Jan 30, 2018 An important departure from traditional project management is that critical chain project management logic:
A) Changes from a late finish to an early start approach. B) Factors in the effects of resource contention. C) Adjusts expected activity durations to reflect a 95 probability of completion on time. D) Creates a separate safety margin for each activity in the project. Title: An important departure from traditional project management is that critical chain project management ... Post by: su on Jan 30, 2018 Content hidden
|