Title: A project manager is using the payback method to make the final decision on which project to ... Post by: Chinnab on Jan 30, 2018 A project manager is using the payback method to make the final decision on which project to undertake. The company has a 10 required rate of return and expects a 4 rate of inflation for the following five years.
What is the discounted payback of a project that has cash flows as shown in the table? Year Cash Flow 0 -100,000 1 20,000 2 50,000 3 50,000 4 25,000 5 500,000 A) 3.4 years B) 2.6 years C) 5.0 years D) 4.2 years Title: A project manager is using the payback method to make the final decision on which project to ... Post by: casssm on Jan 30, 2018 Content hidden
|