Title: A company negotiates a price for two aircraft that includes a reduction in labor on the second ... Post by: tony911t on Jan 30, 2018 A company negotiates a price for two aircraft that includes a reduction in labor on the second aircraft consistent with a 70 learning curve. Suppose the first aircraft took 100 hours.
If the improvement rate changes to 20, how will the total time to complete both aircraft change? A) no change B) -10 hours C) + 10 hours D) -50 hours E) + 50 hours Title: A company negotiates a price for two aircraft that includes a reduction in labor on the second ... Post by: Cologicoon on Jan 30, 2018 Content hidden
Title: A company negotiates a price for two aircraft that includes a reduction in labor on the second ... Post by: tony911t on Jan 30, 2018 Thanks again
|