Title: A company negotiates a price for two aircraft that includes a reduction in labor on the second ...
Post by: tony911t on Jan 30, 2018
A company negotiates a price for two aircraft that includes a reduction in labor on the second aircraft consistent with a 70 learning curve. Suppose the first aircraft took 100 hours.
 
  If the improvement rate changes to 20, how will the total time to complete both aircraft change?
  A) no change
  B) -10 hours
  C) + 10 hours
  D) -50 hours
  E) + 50 hours