Title: Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step ... Post by: Godchaser on Jan 30, 2018 Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings.
Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash. Calculate both the maximum time-savings available on a 25 crash budget and the cost to crash four hours of savings. Activity Normal Duration (hours) Normal Cost () Crash Duration (hours) Crash Cost (S) Immediate Predecessors A 2 10 2 0 None B 3 15 2 23 A C 5 25 4 30 B D 3 20 1 24 C E 6 30 4 45 C F 1 5 1 0 C,E G 7 35 6 50 F H 10 50 7 80 D,G Title: Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step ... Post by: loganhausler on Jan 30, 2018 Content hidden
|