Title: The high-low method is more accurate than the regression method of estimating a cost function.
Post by: vsisto on Jul 1, 2018
The high-low method is more accurate than the regression method of estimating a cost function.
[True or False]


Title: The high-low method is more accurate than the regression method of estimating a cost function.
Post by: Tiadhj on Jul 1, 2018
 False
Explanation:  The regression method is more accurate than the high-low method since it uses all available data to estimate a cost function.


Title: The high-low method is more accurate than the regression method of estimating a cost function.
Post by: vsisto on Jul 1, 2018
TY!


Title: The high-low method is more accurate than the regression method of estimating a cost function.
Post by: Tiadhj on Jul 1, 2018
You're welcome