Title: The budgeted production of Taurus, Inc. is 14,000 units per month. Each unit requires 40 minutes of ... Post by: wizspero on Jul 27, 2018 The budgeted production of Taurus, Inc. is 14,000 units per month. Each unit requires 40 minutes of direct labor to complete. The direct labor rate is $90 per hour. Calculate the budgeted cost of direct labor for the month. (Round any intermediate calculations to the nearest cent and your final answer to the nearest dollar.)
A) $840,000 B) $373,333 C) $1,260,000 D) $31,500 Title: The budgeted production of Taurus, Inc. is 14,000 units per month. Each unit requires 40 minutes of ... Post by: Jslemin on Jul 27, 2018 A
Explanation: A) Budgeted production units for the month14,000 Direct labor time required per unit40 minutes Direct labor hours for budgeted production9,333.33 Direct labor rate per hour$90 Budgeted direct labor cost for the month$840,000 Title: The budgeted production of Taurus, Inc. is 14,000 units per month. Each unit requires 40 minutes of ... Post by: wizspero on Jul 27, 2018 Literally the most helpful website ever
Title: The budgeted production of Taurus, Inc. is 14,000 units per month. Each unit requires 40 minutes of ... Post by: Jslemin on Jul 27, 2018 :monkey:
|