Title: Project Sand Mandala Carrie meticulously calculated the early and late start and finish times for ...
Post by: smolie04 on Nov 29, 2018
Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.

ActivityPredecessorDurationEarly StartEarly FinishLate StartLate Finish
A-10
B-711
CA7
DA1514
EB1119
FB10
GD,E24
HF24
JC28
KG,H,J36

What is the early finish time for activity K?

• 36

• 35

• 34

• 33