Title: If the unit cost of direct materials is $20, direct labor is $12, variable overhead is $2, avoidable ... Post by: Infinitez on Jan 29, 2023 If the unit cost of direct materials is $20, direct labor is $12, variable overhead is $2, avoidable fixed costs are $6,000, unavoidable fixed costs are $5,000 and sunk costs are $9,000, what is the total relevant cost for 300 products?
▸ $25,200 ▸ $24,200 ▸ $15,200 ▸ $16,200 Title: If the unit cost of direct materials is $20, direct labor is $12, variable overhead is $2, avoidable ... Post by: richardbugg on Jan 29, 2023 Content hidden
|