On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to that order.
Hours Required
Receive and process order0.25
Waiting for production to begin1.25
Cutting50.00
Sewing and lettering300.00
Moving materials from one station to another20.00
Waiting for an operation to begin95.00
Packaging35.00
Loading to be shipped0.50
In transit to customer5.00

Calculate the value-added time.

▸ 385 hours

▸ 390.75 hours

▸ 390 hours

▸ 350 hours