Title: Beans Corporation uses a job-order costing system with a single plantwide predetermined overhead ... Post by: nrod1120 on Mar 26, 2023 Beans Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $162,000, variable manufacturing overhead of $2.80 per direct labor-hour, and 60,000 direct labor-hours. Recently, Job K818 was completed with the following characteristics:
If the company marks up its unit product costs by 40% then the selling price for a unit in Job K818 is closest to: (Round your intermediate calculations to 2 decimal places.) ▸ $363.30 ▸ $103.80 ▸ $383.30 ▸ $324.80 Title: Re: Beans Corporation uses a job-order costing system with a single plantwide predetermined overhead ... Post by: HCho0 on Mar 26, 2023 Content hidden
|