Title: Placker Corporation uses a job-order costing system with a single plantwide predetermined overhead ... Post by: Victoria87 on Mar 26, 2023 Placker Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $155,000, variable manufacturing overhead of $3.40 per machine-hour, and 50,000 machine-hours. Recently, Job A881 was completed with the following characteristics:
The total job cost for Job A881 is closest to: (Round your intermediate calculations to 2 decimal places.) ▸ $3,595 ▸ $2,945 ▸ $2,950 ▸ $1,295 Title: Re: Placker Corporation uses a job-order costing system with a single plantwide predetermined overhead ... Post by: Deeclaire on Mar 26, 2023 Content hidden
|