Title: Thach Corporation uses a job-order costing system with a single plantwide predetermined overhead ...
Post by: Befuddled on Mar 26, 2023

Thach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $665,000, variable manufacturing overhead of $3.00 per machine-hour, and 70,000 machine-hours. Recently, Job T321 was completed with the following characteristics:

Number of units in the job30
Total machine-hours90
Direct materials$ 630
Direct labor cost$ 2,880

The unit product cost for Job T321 is closest to:



▸ $117.00

▸ $58.50

▸ $154.50

▸ $51.50


Title: Re: Thach Corporation uses a job-order costing system with a single plantwide predetermined overhead ...
Post by: kidace on Mar 26, 2023
Content hidden