Title: Activity C cannot begin until both activities A and B have been completed. Activity D cannot begin ... Post by: silverbullet on Oct 30, 2016 Activity C cannot begin until both activities A and B have been completed. Activity D cannot begin until activity B has been completed. Which one of the following statements is TRUE?
A) The AOA approach cannot be used at all. B) The AON approach would require more nodes than the AOA approach for these relationships. C) A dummy activity is needed if the AOA approach is used. D) The AON approach would require more arcs than the AOA approach for these relationships. Title: Re: Activity C cannot begin until both activities A and B have been completed. Activity D cannot ... Post by: pennoc on Nov 17, 2016 Content hidden