Title: What is the second step of process costing? Post by: Onxy on Feb 12, 2017 What is the second step of process costing?
A) Summarize the flow of physical units of output. B) Compute output in terms of equivalent units. C) Summarize total costs to account for. D) Compute cost per equivalent unit. E) Assign total costs to units completed and to units in ending work in progress. Title: Re: What is the second step of process costing? Post by: lordington on Feb 12, 2017 Content hidden
|