Title: A PERT chart: (Multiple Choice) Post by: treasurer on Feb 28, 2017 A PERT chart:
A) portrays a project as a network diagram consisting of numbered nodes that represent tasks. B) tracks progress of, and modifications to, project tasks. C) is used to evaluate project risk and time. D) displays a horizontal bar for each project task. Title: Re: A PERT chart: (Multiple Choice) Post by: finially93 on Feb 28, 2017 Content hidden
Title: Re: A PERT chart: (Multiple Choice) Post by: treasurer on Apr 16, 2017 Thanks again
|