Title: Bill is working with a system that uses a bill of materials to project the number of components and ...
Post by: jjolivette on Oct 10, 2017
Bill is working with a system that uses a bill of materials to project the number of components and raw materials needed. It also specifies when they need to arrive. He is most likely using
A) warehousing.
B) material requirements planning.
C) master production scheduling.
D) inventory control.
E) just-in-time.