Title: Disc Company sells 400 discs per week. Purchase order lead time is 3 weeks and the economic order ...
Post by: ruskin on Nov 7, 2017
Disc Company sells 400 discs per week. Purchase order lead time is 3 weeks and the economic order quantity is 900 units. What is the reorder point?
A) 950 units
B) 1,200 units
C) 3,500 units
D) 4,500 units
E) 5,600 units


Title: Re: Disc Company sells 400 discs per week. Purchase order lead time is 3 weeks and the economic ...
Post by: pacho on Nov 7, 2017
Content hidden