Title: Susanna Nanna is the production manager for a furniture manufacturing company. The company produces ... Post by: chimeric on Dec 17, 2017 Susanna Nanna is the production manager for a furniture manufacturing company. The company produces tables (X) and chairs (Y). Each table generates a profit of $80 and requires 3 hours of assembly time and 4 hours of finishing time. Each chair generates $50 of profit and requires 3 hours of assembly time and 2 hours of finishing time. There are 360 hours of assembly time and 240 hours of finishing time available each month. The following linear programming problem represents this situation.
Maximize 80X + 50Y Subject to: 3X + 3Y ≤ 360 4X + 2Y ≤ 240 X, Y ≥ 0 The optimal solution is X = 0, and Y = 120. (a) What would the maximum possible profit be? (b) How many hours of assembly time would be used to maximize profit? (c) If a new constraint, 2X + 2Y ≤ 400, were added, what would happen to the maximum possible profit? Title: Re: Susanna Nanna is the production manager for a furniture manufacturing company. The company ... Post by: miri13 on Dec 17, 2017 (a) 6000, (b) 360, (c) It would not change.
|