The developer of a 40-story high-rise office building desires the shortest possible construction time. What contractual arrangement would be best?
 
  a. Construction management
  b. Design/ build
  c. Design/ bid/ build
  d. Either A or B
  e. None of the above

 Q. 2

A good construction manager has strong _______ skills.
 
  a. Technical
  b. Personal
  c. Managerial
  d. Negotiation
  e. All of the above
Read 36 times
3 Replies

Related Topics

Replies
wrote...
6 years ago
Ans. to #1

D

Ans. to #2

E
Hank Author
wrote...
6 years ago
Thank you

Can you answer the others that I've posted too? Face with Cold Sweat
wrote...
6 years ago
I'll take a quick look at them
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1524 People Browsing
Related Images
  
 222
  
 797
  
 780
Your Opinion
What's your favorite coffee beverage?
Votes: 303