The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.
 a. True
  b. False
  Indicate whether the statement is true or false
Read 33 times
2 Replies
Replies
Answer verified by a subject expert
vulshafer15vulshafer15
wrote...
Top Poster
Posts: 889
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Hummer Author
wrote...
6 years ago
Thank you for answering
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  784 People Browsing
 111 Signed Up Today
Related Images
  
 336
  
 190
  
 628
Your Opinion
Which country would you like to visit for its food?
Votes: 204