The estimated duration of an activity is how long it will take to complete each activity based on
 a. the estimate of resources to be applied to the activity.
  b. the estimate of time for one person to complete the activity.
  c. the amount of time listed in the lessons learned from other projects.
  d. the amount of funds for that activity.
Read 35 times
1 Reply
Replies
Answer verified by a subject expert
babyfacelovebabyfacelove
wrote...
Top Poster
Posts: 903
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

kekule Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Brilliant
dri
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  661 People Browsing
 125 Signed Up Today
Related Images
  
 530
  
 726
  
 1005
Your Opinion