All of the following activities are appropriate upon completion of risk response planning EXCEPT:
 a. The risk register should be updated to reflect the risk response strategies.
  b. The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.
  c. The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments.
  d. A single person should be assigned as the owner of each risk.
Read 50 times
1 Reply
Replies
Answer verified by a subject expert
Sammyfuria2Sammyfuria2
wrote...
Top Poster
Posts: 935
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

zhamila Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1192 People Browsing
Related Images
  
 965
  
 565
  
 227
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 741

Previous poll results: What's your favorite coffee beverage?