asourdillard asourdillard
wrote...
Posts: 639
Rep: 0 0
6 years ago
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of 100,000. Due to slippage on the critical path you need to reduce this activity by three weeks.
 
  If the subcontractor informs you that the activity can be completed in 16 weeks for 200,000, what is the slope for the activity?
  A) 5,000 per week
  B) 33,333 per week
  C) 25,000 per week
  D) 12,500 per week
Read 113 times
1 Reply
Replies
Answer verified by a subject expert
19leekichang19leekichang
wrote...
Top Poster
Posts: 913
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

asourdillard Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1123 People Browsing
Related Images
  
 270
  
 198
  
 548
Your Opinion
Do you believe in global warming?
Votes: 370