Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity?
 
  A) 6, 20
  B) 6, 26
  C) 9, 20
  D) 9, 26
Read 63 times
2 Replies
Replies
Answer verified by a subject expert
dgonzalez228dgonzalez228
wrote...
Top Poster
Posts: 1198
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

jay123 Author
wrote...
6 years ago
Marking this solved
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1154 People Browsing
 104 Signed Up Today
Related Images
  
 1030
  
 285
  
 40
Your Opinion
What's your favorite math subject?
Votes: 293