What is the expected time for activity B?
 
  Thai Construction
  A construction firm from the Phuket Province of Thailand has a five activity project lined up for the coming month. They have had some difficulty getting firm estimates on the activity durations and have resorted to the three time estimates approach to plan the project. The activities and optimistic, most likely, and pessimistic estimates (in days) for each are shown in the table.
 
  Activity Predecessor Optimistic Most Likely Pessimistic
  A - 5 7 10
  B - 11 15 18
  C A 8 12 15
  D - 9 11 12
  E D 6 8 10
 
  A) 14.83
  B) 15.00
  C) 14.67
  D) 14.33
Read 101 times
1 Reply
Replies
Answer verified by a subject expert
grfrfvfbvrgrfrfvfbvr
wrote...
Top Poster
Posts: 916
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

plong717 Author
wrote...

6 years ago
You make an excellent tutor!
ky
wrote...

Yesterday
Good timing, thanks!
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1115 People Browsing
Related Images
  
 469
  
 78
  
 336
Your Opinion
Where do you get your textbooks?
Votes: 372