For risks that have occurred in a project, the team should
 a. track and document the risks and store the information in lessons learned.
  b. expect that the other risks are going to occur so they should increase resources for those tasks impacted.
  c. add more resources to the tasks that are impacted by the risk occurring.
  d. talk about the risk without recording the minutes of the meeting.
Read 79 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
a
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1038 People Browsing
Related Images
  
 633
  
 315
  
 882
Your Opinion
What's your favorite math subject?
Votes: 315