The to-complete performance index is
 a. the amount of funds remaining for the project.
  b. the rate of performance required for the remaining work to finish the project within budget.
  c. the ratio of committed costs remaining to planned costs.
  d. the ratio of planned costs for the work remaining to the budgeted costs of the project.
Read 26 times
1 Reply
Replies
Answer verified by a subject expert
lmslinkardlmslinkard
wrote...
Top Poster
Posts: 886
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Uniquecorn21 Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
Helped a lot
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1545 People Browsing
 113 Signed Up Today
Related Images
  
 1116
  
 684
  
 216
Your Opinion
What's your favorite coffee beverage?
Votes: 274

Previous poll results: Where do you get your textbooks?