If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
 a. Three workers per day
  b. 21 worker-days
  c. Seven days
  d. Additional information is needed to determine the minimum number.
Read 89 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

MADUBUCA76 Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1637 People Browsing
Related Images
  
 441
  
 1353
  
 2546
Your Opinion
What's your favorite math subject?
Votes: 559