To control the project, the project team should collect
 a. data on the actual performance and information about any changes to the project scope, schedule, and budget.
  b. anecdotal information from the project team members.
  c. reports on the amount of money spent because that is the amount of work completed.
  d. the names and descriptions of the resources used on the project.
Read 67 times
1 Reply
Replies
Answer verified by a subject expert
19leekichang19leekichang
wrote...
Top Poster
Posts: 913
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Altysha Author
wrote...

6 years ago
Correct Slight Smile TY
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
Good timing, thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1111 People Browsing
 121 Signed Up Today
Related Images
  
 948
  
 861
  
 911
Your Opinion