× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
g
3
2
J
2
p
2
m
2
h
2
s
2
r
2
d
2
l
2
a
2
s
2
New Topic  
bosh bosh
wrote...
Posts: 762
Rep: 0 0
6 years ago
The critical path in a PERT diagram is the one that:
 
  A) has the most activities on it.
 
  B) has activities that can be delayed and not impact the completion date of the project.
 
  C) takes the longest amount of time.
 
  D) is the most likely to occur.
Read 32 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  714 People Browsing
 114 Signed Up Today
Related Images
  
 251
  
 6044
  
 738
Your Opinion
Do you believe in global warming?
Votes: 370