1. The project manager will conduct one or more kickoff meetings to plan all of the following
EXCEPT:
a. Establishing the project office
b. Getting stakeholder and sponsor endorsement
c. Develop project policies and procedures
d. Developing the project management plan
e. Refining the project management plan

2. Which of the following is true of a project’s objectives?
a. Lack detail
b. Longer time frames
c. Vague measures
d. Contain a measurable outcome

Read 157 times
1 Reply

Related Topics

Replies
Anonymous
wrote...
A year ago
1. The project manager will conduct one or more kickoff meetings to plan all of the following
EXCEPT:
a. Establishing the project office
b. Getting stakeholder and sponsor endorsement
c. Develop project policies and procedures
d. Developing the project management plan
e. Refining the project management plan

This meeting would follow definition of the base elements for the project and other project planning activities.

2. Which of the following is true of a project’s objectives?
a. Lack detail
b. Longer time frames
c. Vague measures
d. Contain a measurable outcome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1142 People Browsing
Related Images
  
 173
  
 782
  
 279
Your Opinion
Which is the best fuel for late night cramming?
Votes: 145

Previous poll results: Do you believe in global warming?