The following data for the telephone company pertain to the production of 450 rolls of telephone wire during June. Selected items are omitted because the costing records were lost in a windstorm.

   Direct Materials (all materials purchased were used.)

   Standard cost per roll:  a  kilograms at $4.00 per kilogram.
   Total actual cost:  b  kilograms costing $9,600.
   Standard cost allowed for units produced was $9,000.
   Materials rate variance:  c .
   Materials efficiency variance was $80 unfavourable.

   Direct Manufacturing Labour

   Standard cost is 3 hours per roll at $8.00 per hour.
   Actual cost per hour was $8.25.
   Total actual cost:  d .
   Labour rate variance:  e .
   Labour efficiency variance was $400 unfavourable.

Required:
Compute the missing elements in the report represented by the lettered items.
Textbook 
Cost Accounting: A Managerial Emphasis, Canadian Edition

Cost Accounting: A Managerial Emphasis, Canadian Edition


Edition: 7th
Authors:
Read 90 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
a.
Standard cost per roll   = $9,000/450 = $20.00
Standard number of kilograms per roll   = $20/$4 = 5 kilograms per roll

b.
Actual kilograms   = ($9,000 + $80)/$4 = 2,270 kilograms

c.
Materials rate variance   = $9,600 - ($9,000 + $80)
   = $520 unfavourable
d.
Total standard labour cost of actual hours   = (450 × 3 × $8) + $400 = $11,200
   Actual hours   = $11,200/$8 = 1,400
   Total actual cost   = 1,400 × $8.25 = $11,550
e.
Labour rate variance   = $11,550 - $11,200 = $350 unfavourable
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1433 People Browsing
Related Images
  
 1314
  
 321
  
 1115
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 824