How should you go about assigning a date to each task?
 
  a. Only assign dates on which you have no other commitments. b. Work backward from your projects deadline.
  c. Work forward from the time you were notified of the project.
 
  d. Projects to be completed in two weeks or less dont usually need dates.
Read 40 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
b