The architect/engineer relies on whom for assurance that the monthly estimate of work performed as submitted by the contractor is valid?
 
  A. No one, the architect/engineer must verify this.
   B. The contractor whose estimate is guaranteed by a bonding company.
   C. The resident project representative.
   D. The owner.
   E. a notary public.

 Q. 2

In most states, the parties to a construction contract can agree to resolve disputes through binding arbitration
 
  A. with the consent of the parties only after a dispute actually arises.
   B. at the time of signing the construction contract.
   C. only if neither party chooses to litigate in court.
   D. only on disputes of less than 50,000.
   E. none of the above.

 Q. 3

What types of damages are contractors entitled to for delay claims?
 
  What will be an ideal response?
Read 18 times
2 Replies
Replies
Answer verified by a subject expert
merana.potrosmerana.potros
wrote...
Posts: 315
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Ebridges85 Author
wrote...
6 years ago
Upwards Arrow All were right, you're seriously the best
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  846 People Browsing
Related Images
  
 373
  
 773
  
 368
Your Opinion
What's your favorite funny biology word?
Votes: 335

Previous poll results: Where do you get your textbooks?