Transcript
Project Management
Module 8: Project Case Study Notes
Assignment 1: Preliminary Evaluation
Assess current state of project organization
Confirm formal and informal communications channels
Study deadlines, financial penalties, risks
Evaluate impact and probability
Check state of existing contracts, and new contracts needed
Assignment 2: Regarding Individual and Team Issues
Review:
Planning and costing calculations
Time & cost control procedures
Pre-design stages
The project manager:
Provides advice on all aspects of the project during feasibility (detailed investment appraisals, economic analyses, cost-benefit analyses, and financial modeling)
Co-ordinates the development of the project brief (formalizes the client requirements)
Advises on the appointment of specialist feasibility-study consultants
Provides monitoring and co-ordination of all approvals and consents
Establishes an overall conceptual program for the project
Establishes cost control and reporting procedures (Implementation, Monitoring, and Control System-IMCS)
Formation of Project Team
PM advises the client on the selection and appointment of external consultants
Establishes the project team and initiates the project team-building process
Develops a project task responsibility matrix (TRM) which links individual responsibilities with time deadlines
Develops proposed monitoring and control systems for planning, authorizing, controlling, and directing all aspects of the project team
Evolves the team building process, including standards and targets
Provides levels and standards of leadership
Provides life-cycle leadership
Interfaces with client and organization
Negotiates or coordinates negotiation with suppliers and clients
Manages project resources
Monitors and controls project status
Identifies issues and problem areas
Resolves team conflicts
Conflict & stress management & motivation and reward systems
Design Stages
In the design stage, the project manager:
Coordinates all aspects of design
Develops initial time, cost, & quality objectives
Develops of project statement of works (SOW)
Develops a work breakdown structure (WBS)
Develops a cost accounting code (CAC) based on the WBS elements and primes each work package with a budget total using a computerized database estimating system (CDES)
Using CAC system, develops a precedence diagram using CPM or PERT, develops a draft master schedule (DMS)
Presents the DMS to the client, and analyzes time, cost, & quality trade-offs
Applies the trade-off solution to generate a PMS
Ensure the designs comply with all internal and external design requirements: including statutory requirements
If needed, coordinates the design and implementation of a prototype
Sets up cost and budget plan
Sets up a suitable EVA reporting system
Tender and Award
Inviting prices for work based on the SOW
Complete a pre-tender cost check
Coordinates the preparation of full SOW
Advises on tender to be accepted
Insurance, performance bonds, tendering company checks
Project Execution
Coordinates the efforts of the design team
Establishes a suitable performance monitoring and control system
Establishes a suitable cost monitoring and control system
Establishes a suitable quality management & control system
Operates an EVA variance and analysis system
Isolates the variances and records them as part of a PVAR system
Uses these Variance reports or executive recommendations for action
Monitors and controls the team development and team building process
Tactical leadership at all levels
Monitors and controls project team performance
Etc, etc.
Project commissioning and use
Advises on effective method for commissioning the project
Advises on making use of the project
Appoints external specialists
Develops suitable procedures for the collection and use of feedback
Risk Management
Contractors and suppliers: risk assessment
Tenants, consultants, contracts with associated companies or partners
Risk Grid (Plotting impact vs probability)
Organization structure
Create OBS
Create communication link diagram
Time planning and control: Create Gantt Chart
Cost Planning and Control
EVA system
Table 8.16 Rates of progress and costs at week 8
Progress (%)
Costs (£)
Planned
Actual
Planned
Actual
Demolition
100
100
12 000
12 000
Structural
75
60
9 750
10 000
Alterations
50
50
12 500
14 000
Redecoration
25
20
2 000
2 000
Values for budgeted cost of the works performed (BCWP), budgeted cost of the works scheduled (BCWS) and actual cost of the works performed (ACWP) are now as given in Table 8.17.
Table 8.17 Schedule of costs at week 8
Planned
Actual
Budget
BCWP
BCWS
ACWP
Demolition
100%
100%
12 000
12 000
12 000
12 000
Structural
75%
60%
13 000
7 800
9 750
10 000
Alterations
50%
50%
25 000
12 500
12 500
14 000
Redecoration
25%
20%
8 000
1 600
2 000
2 000
The cost variance (CV), schedule variance (SV), cost variance index (CVI), and schedule variance index (SVI) values can now be calculated on the basis of the following formulae:
Table 8.18 Schedule of costs and parameters at week 8
Budget
BCWP
BCWS
ACWP
CS
SV
CVI
SVI
Demolition
12 000
12 000
12 000
12 000
0
0
1
1
Structural
13 000
7 800
9 750
10 000
2 200
?1 950
0.78
0.8
Alterations
25 000
12 500
12 500
14 000
?1 500
0
0.893
1
Redecoration
8 000
1 600
2 000
2 000
?400
?400
0.8
0.8
Positive variance values are good as they represent works that are ahead of programme and/or under cost; similarly, index values greater than 1.0 are good. Negative variances or indices less than 1.0 are unfavourable. A glance at the last four columns of the table above shows that the variance values are all zero or negative, giving corresponding indices of less than 1.0.
This process would be repeated for whatever reporting cycle is required. The process would typically be carried out on a weekly basis, with the analysis being used as the basis for the cost- and progress-reporting system. Longer-term tracking might reveal the figures shown in Table 8.19.
Table 8.19 CV and SV values for the project as a whole
Week
1
2
3
4
5
6
7
8
Demolition
CV
0
0
100
?100
0
0
0
0
SV
0
0
0
0
0
0
0
0
Structural
CV
0
?250
?350
?500
?900
?1300
?1700
?2200
SV
0
0
?150
?350
?800
?1200
?1400
?1950
Alterations
CV
0
0
0
0
0
?250
?1000
?1500
SV
0
0
100
?250
0
0
0
0
Redecoration
CV
0
300
0
250
?400
0
0
?400
SV
0
0
0
0
0
0
0
?400
CV total
50
?250
?350
?1300
?1550
?2700
?4100
SV total
?50
?600
?800
?1200
?1400
?2350
CM System
Outline/Map of all information databases and their relationship to each other.