Elon Musk's latest initiative is funding the first manned voyage to the sun. He has identified seven activities, labeled only as A through G (for proprietary reasons). The normal duration in months and cost in millions of dollars for each activity and the expedited times and costs are shown in the table.


Activity

Predecessor
Normal Duration
Normal Cost
Crash Duration
Crash Cost
A--7$20005$3000
B--8$15006$2000
CA12$250010$2900
DB13$300010$4200
EB15$400012$5500
FC, E10$32008$4000
GD7$18006$2200

If the project manager wishes to finish the project in 30 months, what is the lowest cost achievable? If the project manager must work with a budget of a paltry $20,000 million, what is the fastest completion time?
Textbook 
Introduction to Management Science

Introduction to Management Science


Edition: 13th
Author:
Read 107 times
1 Reply
Replies
Answer verified by a subject expert
Ablaze123Ablaze123
wrote...
Posts: 198
5 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

elmajn Author
wrote...

5 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  972 People Browsing
 167 Signed Up Today
Related Images
  
 24
  
 1267
  
 1024
Your Opinion
Which is the best fuel for late night cramming?
Votes: 146

Previous poll results: Where do you get your textbooks?