Nalu Nalu
wrote...
Posts: 823
Rep: 0 0
6 years ago
The company is using a lot size of 700 units per order. Calculate the safety stock required for a cycle service level of 97.5. In addition, what is the cost difference between the current policy and using the EOQ lot size? (safety stock/cost) The expected annual demand is 123,670 units. The standard deviation for a week is 345 units. The ordering cost is 200 and the carrying cost is 3.00 per unit per year. In addition, the lead time is 3 weeks and there are 52 weeks per year.
 a. 1171 units/24,202 c. 1171 units/24,202
  b. 8306 units/36,384 d. 4060 units/12,182
Read 46 times
1 Reply
Replies
Answer verified by a subject expert
DCAV1DCAV1
wrote...
Top Poster
Posts: 1097
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Nalu Author
wrote...

6 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  475 People Browsing
Related Images
  
 560
  
 186
  
 1454
Your Opinion
How often do you eat-out per week?
Votes: 81

Previous poll results: What's your favorite coffee beverage?