Which of the following events excuses a promisor from performing his or her contractual obligations?
 A) a riot
 B) a shortage of materials necessary for production of goods and/or provision of services called for under the contract
 C) an unanticipated increase in the cost of performance
 D) destruction of the subject matter through no fault of either party
Read 24 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
D