6 years ago
Which statement about this Gantt chart is BEST?
 
  A) Activity a has a duration that could be as short as 1 day and as long as 10.
  B) Activity b probably has activity a as a predecessor.
  C) No progress has been made on activity c.
  D) Activity d is the longest activity.
Read 31 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
B