A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:
 a. CPM addresses the risk associated with duration estimates whereas PERT does not.
  b. unlike CPM, PERT estimates only when there is no risk of uncertainty.
  c. CPM involves more work than PERT because it requires several duration estimates.
  d. PERT uses different duration estimates whereas CPM uses one specific duration estimate.
Read 52 times
2 Replies
Replies
Answer verified by a subject expert
bhodgesbhodges
wrote...
Top Poster
Posts: 1244
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

checkitout Author
wrote...
6 years ago
Cheers!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  941 People Browsing
Related Images
  
 112
  
 166
  
 6689
Your Opinion
How often do you eat-out per week?
Votes: 80