Latest finish time (LF) is the latest time by which a specific activity must be
 a. started in order for the entire project to be finished by its required completion time.
  b. completed in order for the entire project to be finished by its required completion time.
  c. started in order for the entire project to be started by its required completion time.
  d. completed in order for the entire project to be started by its required completion time.
Read 67 times
1 Reply
Replies
Answer verified by a subject expert
CologicoonCologicoon
wrote...
Top Poster
Posts: 949
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

adasdsdew Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1021 People Browsing
Related Images
  
 315
  
 357
  
 381