The typical time horizon for developing a Master Production Schedule (MPS) is
A) 6 months to 1 year.
B) up to 3 months.
C) weekly.
D) daily.
Textbook 
Managing Supply Chain and Operations: An Integrative Approach

Managing Supply Chain and Operations: An Integrative Approach


Edition: 1st
Authors:
Read 82 times
2 Replies
Replies
Answer verified by a subject expert
fc10fc10
wrote...
Posts: 398
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

mcv4u Author
wrote...
6 years ago
Thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1062 People Browsing
Related Images
  
 279
  
 233
  
 269