In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in iterations (sprints) that are normally:
 a. no more than one calendar year
  b. a variable length depending on project scope
  c. a fixed length of two or four weeks
  d. assigned to one person on the team
Read 29 times
1 Reply
Replies
Answer verified by a subject expert
alohacharlesalohacharles
wrote...
Top Poster
Posts: 910
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...

6 years ago
Thank you, thank you, thank you!
wrote...

Yesterday
Correct Slight Smile TY
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  726 People Browsing
Related Images
  
 611
  
 758
  
 292
Your Opinion
Who will win the 2024 president election?
Votes: 8
Closes: November 4