Consider a project composed of activities X and Y having equal length and performed in that order.
 
  Both activities can be laddered such that the first half of each activity is the predecessor for its own second half, so X1 precedes X2 and Y1 precedes Y2. The first half of X1 is also the predecessor for Y1. If the laddering procedure were performed again activities X and Y would be divided in four parts each, with precedence working as it did in the first split. Derive an expression for the minimum length of the project as laddering increases.
Read 56 times
1 Reply
Replies
Answer verified by a subject expert
abenhadabenhad
wrote...
Top Poster
Posts: 859
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
This verified answer contains over 150 words.
1

Related Topics

nawal Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  925 People Browsing
 109 Signed Up Today
Related Images
  
 816
  
 99
  
 367
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 379