zhamila zhamila
wrote...
Posts: 705
Rep: 0 0
6 years ago
Use the earned value table for Project Makeready to determine the schedule variance.
 
  Activity 7 14 21 28 35 42 49 Plan  Complete
  Install fixtures 325 250 575 100
  Refinish floors 550 85 635 100
  Replace doors 350 275 625 100
  Complete tiling 1,200 565 1,765 80
  Install back door 875 225 1,100 70
  Landscaping 200 350 550 25
  Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
  Monthly Act 550 550 550 1,100 1,650 550 1,100
  A) -1,896
  B) -1,096
  C) -800
  D) -206
Read 69 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
B
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  737 People Browsing
Related Images
  
 288
  
 271
  
 254
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 485

Previous poll results: Where do you get your textbooks?