A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.
 
  Activity Average Worst-Case
  A 14 21
  B 20 28
  C 16 22
  D 8 15
  E 9 18
  F 11 18
  A) 44 days
  B) 6 days
  C) 17 days
  D) 9 days
Read 540 times
8 Replies
Replies
Answer verified by a subject expert
ohssiohssi
wrote...
Top Poster
Posts: 929
Rep: 0 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...
4 years ago
thank you
wrote...
3 years ago
thanks
wrote...
3 years ago
thnak you
wrote...
3 years ago
Thank
wrote...
3 years ago
thank
wrote...
3 years ago
Thank
wrote...
2 years ago
thanku
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1052 People Browsing
Related Images
  
 70
  
 307
  
 820
Your Opinion
How often do you eat-out per week?
Votes: 81