The earned value to date divided by the planned value of work scheduled to be performed is the:
 
  A) Cost performance index.
  B) Budgeted cost at completion index.
  C) Budget efficiency index.
  D) Schedule performance index.
Read 49 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D