Which of the following statements regarding critical paths is true?
 
  A) The shortest of all paths through the network is the critical path.
  B) Some activities on the critical path may have slack.
  C) Every network has only one critical path.
  D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
  E) The duration of the critical path is the average duration of all paths in the project network.
Read 61 times
1 Reply
Replies
Answer verified by a subject expert
garyrangel12garyrangel12
wrote...
Top Poster
Posts: 926
Rep: 2 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

abbiedigings Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Just got PERFECT on my quiz
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1793 People Browsing
Related Images
  
 1447
  
 640
  
 646
Your Opinion
Which country would you like to visit for its food?
Votes: 262