Altysha Altysha
wrote...
Posts: 693
Rep: 0 0
6 years ago
Determine which activities should be crashed to shorten the project by 2 days.
 
  What will be an ideal response?
Read 43 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
Answer: Crash C by 1 day, E by 1 day
Altysha Author
wrote...
6 years ago
I sincerely appreciate this help!