_____ are unplanned responses to risk events used when project teams do not have contingency plans in place.
 a. Workarounds b. Fallback plans
  c. Contingency plans d. Triggers
Read 50 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
a